Written question asked by John Healey (Labour) on Monday, 19 July 2021, in the House of Commons. It was due for an answer on Wednesday, 21 July 2021. It was answered by Jeremy Quin (Conservative) on Wednesday, 21 July 2021 on behalf of the Ministry of Defence.


AWE Aldermaston

Question

To ask the Secretary of State for Defence, what were the total constructive losses to his Department for the termination of Project Hydrus in 2010.

Answer

Following the decision not to proceed with construction activities on Project Hydrus, the final write off cost for the termination of the project was £117.7 million and components valued at £71 million were incorporated into the joint UK/French hydrodynamic capability established under the TEUTATES Treaty.