Written question asked by Neale Hanvey (Alba Party) on Tuesday, 18 April 2023, in the House of Commons. It was due for an answer on Tuesday, 25 April 2023 (named day). It was answered by Andrew Murrison (Conservative) on Tuesday, 25 April 2023 on behalf of the Ministry of Defence.


Radioactive Waste: Dalgety Bay

Question

To ask the Secretary of State for Defence, what proportion of the pollutant linkage identified by the Scottish Environment Protection Agency in the foreshore areas of Dalgety Bay has been cleared since May 2021.

Answer

Until such time as the works are completed, it is not possible to calculate the proportion of pollutant linkage identified by the Scottish Environment Protection Agency in the foreshore areas of Dalgety Bay that has been cleared since May 2021.

However, to date, 85% of the work has been completed with 3,200 particles of contamination being removed from 7,000 cubic meters of foreshore.


Secondary information

Type
Written question
Reference
181494
Session
2022-23
Subjects
Radioactive waste Waste management Dalgety Bay
Contains statistics
Yes
Link
View this Written question on www.parliament.uk