Written question asked by Neale Hanvey (Alba Party) on Tuesday, 18 April 2023, in the House of Commons. It was due for an answer on Tuesday, 25 April 2023 (named day). It was answered by Andrew Murrison (Conservative) on Tuesday, 25 April 2023 on behalf of the Ministry of Defence.
Radioactive Waste: Dalgety Bay
- Question
-
To ask the Secretary of State for Defence, what recent estimate he has made of the cost of the remediation works at Dalgety Bay.
- Answer
-
The current Approved Budget Level for the project is circa £15 million.
The actual cost will remain undetermined until the work is completed and any risks addressed.
Secondary information
- Type
- Written question
- Reference
- 181501
- Session
- 2022-23
- Subjects
- Costs Radioactive waste Waste management Dalgety Bay
- Contains statistics
- Yes
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2023-04-25 12:37:09 +0100
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/commons/2022-23/181501
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/commons/2022-23/181501
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/commons/2022-23/181501