Written question asked by John Healey (Labour) on Tuesday, 10 May 2022, in the House of Commons. It was due for an answer on Thursday, 12 May 2022. It was answered by Jeremy Quin (Conservative) on Wednesday, 18 May 2022 on behalf of the Ministry of Defence.
AWE Aldermaston
- Question
-
To ask the Secretary of State for Defence, what his timeframe is for completing the construction of the PEGASUS facility.
- Answer
-
The original and current approved costs and the current in-service dates for Project Mensa and Project Pegasus are as follows:
Project
Original Cost Approved in 2011
Current Approved Cost
Approved In-service Date
MENSA
£734 million
£1996 million
2024
PEGASUS
£634 million
£634 million
Material Handling Store - 2025 Manufacture Capability – 2030
Secondary information
- Type
- Written question
- Reference
- 44
- Session
- 2022-23
- Grouped for answer
- Yes
- Subjects
- Construction AWE Aldermaston
- Contains statistics
- Yes
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2022-05-18 17:09:02 +0100
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/commons/2022-23/44
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/commons/2022-23/44
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/commons/2022-23/44