Written question asked by Ben Obese-Jecty (Conservative) on Tuesday, 4 November 2025, in the House of Commons. It was due for an answer on Tuesday, 11 November 2025. It was answered by Luke Pollard (Labour) on Monday, 17 November 2025 on behalf of the Ministry of Defence.


RAF Marham

Question

To ask the Secretary of State for Defence, what the timeline is for completion of new service accommodation at RAF Marham.

Answer

Four new Single Living Accommodation blocks are under construction at RAF Marham. The first block is scheduled for completion and handover for occupation on 4 December 2025, with two further blocks due for completion by February 2026. The final block is planned for completion in April 2027.

There are no plans for the construction of new Service Family Accommodation at RAF Marham.