Written question asked by John Whitby (Labour) on Wednesday, 5 November 2025, in the House of Commons. It was due for an answer on Tuesday, 11 November 2025. It was answered by Kanishka Narayan (Labour) on Tuesday, 18 November 2025 on behalf of the Department for Science, Innovation and Technology.


Building Digital UK: Contracts

Question

To ask the Secretary of State for Science, Innovation and Technology, whether her Department has made provisions for the recovery of public funds from contractors who fail to deliver on Building Digital UK contracts.

Answer

Payments to suppliers for delivery under Project Gigabit contracts are made once a gigabit capable connection is available to the premises. Where a supplier fails, the supplier is required to repay any public money paid through the contracts for premises which do not reach this point.

In May 2025, Building Digital UK (BDUK) and Full Fibre mutually agreed to terminate the Project Gigabit contract for the Peak District, which included some premises in the Derbyshire Dales constituency. This contract did not reach a stage where gigabit-capable connections were being delivered and therefore there was no requirement for any funding to be repaid by the supplier.


Secondary information

Type
Written question
Reference
88542
Session
2024-26
Subjects
Contracts Finance Building Digital UK
Link
View this Written question on www.parliament.uk