Written question asked by Pippa Heylings (Liberal Democrat) on Monday, 13 July 2026, in the House of Commons. It was due for an answer on Wednesday, 15 July 2026. It was answered by Michael Shanks (Labour) on Tuesday, 21 July 2026 on behalf of the Department for Energy Security and Net Zero.
Energy: Artificial Intelligence
- Question
-
To ask the Secretary of State for Energy Security and Net Zero, what estimate he has made of the data-centre capacity required to deliver the grid applications identified in the Interim AI Adoption Plan: Clean Energy.
- Answer
-
The Department has not produced an estimate of the data-centre capacity required specifically for the grid applications identified in the Interim AI Adoption Plan: Clean Energy.
The Government is, however, undertaking broader analysis of the potential growth in demand from AI and data centres as part of ongoing work on energy demand projections, electricity network planning and AI infrastructure policy.
Secondary information
- Type
- Written question
- Reference
- 18225
- Session
- 2026-27
- Subjects
- Energy Artificial intelligence Data centres
- Contains statistics
- Yes
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2026-07-21 10:38:22 +0100
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/commons/2026-27/18225
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/commons/2026-27/18225
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/commons/2026-27/18225