HMS Lancaster

Question

To ask the Secretary of State for Defence, what was the cost of the latest refit of HMS Lancaster.

Answer

The costs of the most recent deep maintenance periods (Docking Periods) for the specified Type 23 frigates are as follows:

  • HMS Lancaster – £67.6 million - May 2017 - June 2020 - 156 weeks
  • HMS Iron Duke – £102.9 million - May 2019 - May 2023 - 208 weeks
  • HMS Richmond – £72.0 million – October 2017 - June 2020 –126 weeks.

These periods of planned deep maintenance were undertaken to sustain the ships’ operational capability and recertify the ships’ safety to operate in accordance with the Programme of Record (the ships’ sustainment) under the last government


Secondary information

Type
Written question
Reference
1918
Session
2026-27
Grouped for answer
Yes
Subjects
Costs Repairs and maintenance HMS Lancaster
Link
View this Written question on www.parliament.uk