Written question asked by Ben Obese-Jecty (Conservative) on Friday, 28 August 2026, in the House of Commons. It was due for an answer on Wednesday, 2 September 2026. It was answered by Luke Pollard (Labour) on Tuesday, 8 September 2026 on behalf of the Ministry of Defence.
Astute Class Submarines
- Question
-
To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Astute Boats 1-7, whether delays have impacted the in-water phase for Boat 6.
- Answer
-
In September 2025, the sixth Astute Class submarine, HMS AGAMEMNON was commissioned into the Royal Navy and is undertaking the final stages of her in-water commissioning, before a handover to the Royal Navy to undertake sea trials.
Achilles, the seventh and last boat of the class, remains at an advanced stage of build in Barrow-in-Furness and work to recover from the impact of the fire in the Devonshire Dock Hall is progressing well.
The planned in-service dates for Royal Navy submarines are withheld as disclosure would, or would be likely to, prejudice the capability, effectiveness, or security of the Armed Forces.
Secondary information
- Type
- Written question
- Reference
- 23307
- Session
- 2026-27
- Grouped for answer
- Yes
- Subjects
- Nuclear submarines Astute class submarines
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2026-09-08 12:00:40 +0100
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/commons/2026-27/23307
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/commons/2026-27/23307
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/commons/2026-27/23307