Skip to main content

Written question asked by Alec Shelbrooke (Conservative) on Monday, 15 June 2026, in the House of Commons. It was due for an answer on Wednesday, 17 June 2026. It was answered by Luke Pollard (Labour) on Wednesday, 24 June 2026 on behalf of the Ministry of Defence.


Future Combat Air System: Expenditure

Question

To ask the Secretary of State for Defence, what is the total spend to date on the Tempest project, including pre-concept and early concept phases.

Answer

Since its inception, the UK Government has invested over £2 billion on the Future Combat Air System (FCAS) Tempest project. In addition to this, the project has attracted over £700 million of private investment since the programme began.


Secondary information

Type
Written question
Reference
9540
Session
2026-27
Subjects
Expenditure Future combat air system
Link
View this Written question on www.parliament.uk