Written question asked by Lord Strathcarron (Non-affiliated) on Monday, 21 July 2025, in the House of Lords. It was due for an answer on Monday, 4 August 2025. It was answered by Lord Wilson of Sedgefield (Labour) on Thursday, 31 July 2025 on behalf of the Department for Energy Security and Net Zero.


Energy Supply and National Grid: Costs

Question

To ask His Majesty's Government why the cost of upgrading the electricity grid is estimated at £60 billion in the report Clean Power 2030, published on 5 November 2024 by the National Energy System Operator, and at £80 billion in the Ofgem press release on 1 July about initial investment in energy security; and whether they will update their costing.

Answer

The £80bn cost estimate in Ofgem’s Draft Determinations for RIIO ET3, which covers 2026/27 to 2030/31, is not exclusively spending required to deliver the transmission network needed to deliver 2030 Clean Power, but also takes into account wider operational costs such as maintenance of existing assets, and includes some spend beyond 2030. Ofgem and NESO regularly review and update their cost estimates for electricity networks.


Secondary information

Type
Written question
Reference
HL9714
Session
2024-26
Subjects
Costs Energy supply National grid
Contains statistics
Yes
Link