Written question asked by Lord Jopling (Conservative) on Thursday, 11 September 2025, in the House of Lords. It was due for an answer on Thursday, 25 September 2025. It was answered by Lord Hendy of Richmond Hill (Labour) on Thursday, 25 September 2025 on behalf of the Department for Transport.


M6: Bridges

Question

To ask His Majesty's Government, during the building of eight new bridges on the M6 in Cumbria, how many nights will (1) both carriageways be closed and (2) one carriageway be closed.

Answer

National Highways are still determining the optimal construction methodology, which will consider how to minimise the number of closures for both or one carriageway. This includes consideration of various techniques, such as Enhanced Mobile Carriageway Closures, to employ short-term rolling roadblocks that could remove the need for some full overnight closures.

Until this work is complete, National Highways are unable to confirm the number of nights when either one or both carriageways will be closed. However, due to the need to replace several bridge decks in their entirety, full closures will be required to undertake work such as high-risk demolition activity.

National Highways will endeavour to minimise disruption to road users, including freight, and the local communities that live close to Lune Gorge, whilst ensuring safe and efficient delivery of the project.


Secondary information

Type
Written question
Reference
HL10457
Session
2024-26
Subjects
Construction Bridges Cumbria M6
Contains statistics
Yes
Link
View this Written question on www.parliament.uk