Written question asked by Lord Moylan (Conservative) on Tuesday, 23 June 2026, in the House of Lords. It was due for an answer on Tuesday, 7 July 2026. It was answered by Lord Hendy of Richmond Hill (Labour) on Tuesday, 7 July 2026 on behalf of the Department for Transport.


High Speed 2 Line: Iron and Steel

Question

To ask His Majesty's Government what percentage of the total steel requirement for HS2 has been procured.

Answer

94% of structural steel and 90% of the steel rebar required for the HS2’s Main Works Civils has been procured. Assessments from the Main Works Contractors working on the Civils structures indicate that around 70% of Rebar and over 80% of Structural Steel required across the programme has been delivered.

Steel procurement has also progressed for other aspects of the programme; however, exact percentages are not available at this time for the Stations or Systems contracts as the designs are under development alongside ongoing HS2 reset activities.


Secondary information

Type
Written question
Reference
HL1225
Session
2026-27
Subjects
Iron and steel Procurement High Speed 2 line
Contains statistics
Yes
Link
View this Written question on www.parliament.uk