Mr. Grogan: To ask the Minister of Agriculture, Fisheries and Food if he will publish the Environment Agency's report on the serious
flooding in autumn and winter 2000; and if he will make a statement. [154898]
Mr. Morley: I am today publishing this report, copies of which are being placed in the House Libraries. Copies of the regional
reports will be placed in the Libraries by 30 March. I welcome publication of this report which I commissioned the Environment
Agency to produce, in partnership with the other bodies responsible for responding to the flooding, particularly local authorities
and the emergency services.
The report shows that since last October we have seen the worst flooding for half a century, following the wettest autumn on record.
Thankfully no loss of life was directly associated with the floods, though 10,000 properties suffered flooding--some repeatedly--and
I again extend the Government's sympathies to all those who were affected.
I endorse the key finding that the Agency, and those responsible for the emergency response, performed well. I am particularly
pleased to note that the seamless and integrated service of flood forecasting, warning and response, for which I called after the
Easter 1998 floods, was delivered in most if not all areas. I am also pleased to note that in a number of localities the emergency
response arrangements benefited from exercises conducted last summer between the Environment Agency, local authorities and the
emergency services. The new flood warning codes, introduced by the Agency within weeks of the floods, also worked well.
I want to thank the Agency, and all the other organisations and individuals involved, for their efforts in response to the flooding.
This involved many hours of long, hard work, rapid decisions which needed to be made, and also individual acts of bravery, for which
the country must express its gratitude. The effects of the flooding would almost certainly have been much worse were it not for
their efforts.
Nevertheless, the report identifies some further lessons to be learned, the key ones being: The flood warning arrangements worked
well but there are some detailed lessons for further improvement. I have asked the Agency to provide me with their proposals for
implementing changes by September 2001. Also, the report notes some deficiencies in the weather forecasts received by the Agency. A
review will be taken forward by the Environment Agency in conjunction with the Met Office, to report by September 2001. There is a
need for the current Home Office review of local authority emergency planning arrangements to take account of the lessons learned
from the floods. There remains some confusion in the minds of the public about responsibility for measures to prevent flooding, and
for responding to it. The key to sound action is planning, partnership and provision of information. Through the Ministry's High
Level Targets, operating authorities are required to provide policy statement which will indicate flood risk locally and how it will
be managed, and to describe local partnerships. Such statements are due to be completed soon. These statements will provide
information on "assumed" responsibility which will provide a useful basis for determining if further action on attribution is
necessary in specific instances and developing a sound local partnership. Provision of a "one stop shop" may then be possible by
local agreement. We have a High Level Target in place for the Environment Agency to organise a programme of local and regional
emergency exercises and should also conduct a national emergency exercise during the course of 2001. While local and regional
exercises should continue, I have accepted the Agency's recommendation that it is unnecessary to conduct a national exercise this
year. I shall consider with the Agency the timetable for a future national exercise. We need to determine the appropriate level of
investment in flood and coastal defence. Substantial increases were made in the Comprehensive Spending Review and the 2000 Spending
Review. An additional £51 million was announced in November, and we have also put together an £11.6 million package to fund the
exceptional costs of the Environment Agency in responding to the flooding and in undertaking emergency repairs. However, I recognise
that we need to be ready to consider whether further expenditure may be justified. We have already instituted additional research to
identify in broad terms what future investment may be required so that this can be considered in future spending reviews. Other
developments such as strategic catchment studies should assist in the future production of more realistic needs-based expenditure
programmes. We have established a series of High Level Targets to ensure Government policy for flood and coastal defence is
delivered by the operating authorities and others. One group of targets requires the Environment Agency to establish a database of
flood and coastal defences and to record information on their condition, based on inspections undertaken by the operating
authorities. The database is an important development, for which MAFF is currently contributing towards the cost; we will consider
whether additional funding is needed. It is also necessary to ensure that inspections of defences are completed by the operating
authorities accurately and to time. I am asking the Environment Agency to report on this, as part of their report on the inspections
and assessment of flood risk required under the High Level Targets. The Environment Agency's report raises questions about the
process for making investment decisions. I have asked the Agency to provide me with supporting evidence by September 2001 and I will
consider with them, and the other operating authorities, whether changes are required. This issue will be relevant to the review,
already under way, of the priority scoring arrangements for consideration of MAFF financial support for flood and coastal defence
schemes. Also under way is a review of the current funding arrangements for flood and coastal defence. I shall ensure that relevant
recommendations in the report are considered by the Review Steering Group. The Agency has also undertaken to carry forward further
reviews and studies which I anticipate receiving with interest.
My right hon. Friend the Deputy Prime Minister was right when, on 31 October 2000, Official Report, column 607, he referred to the
effects of the earlier violent storm as a "wake up call". We can certainly expect climate change to mean that events of this type
will occur more frequently in future. Another inevitable fact is that Governments--past, present and future--cannot prevent all
flooding; but where it is sensible and sustainable to do so, we can take further action to reduce the risk.
We can also take action to ensure that as a nation we are prepared to deal with the effects of severe weather, including but not
limited to flooding, and that our key national infrastructure can withstand these effects. This is a matter on which we are working
closely with local authorities and other key players through the Central Local Partnership.
In summary, if it had not been for the effective response of the Agency and others, the flooding would have had much more serious
effects than it did. There are still lessons to be learned, but we have all come a long way since the flooding three years ago.