To ask the Secretary of State for Housing, Communities and Local Government, further to the answer of 25 February 2025, to Question 33500, on Eden Project: Morecambe, what assessment has been made by the his Department of whether the Eden Project North is able to provide its side of the...
To ask the Secretary of State for Housing, Communities and Local Government, further to the answer of 25 February 2025, to Question 33500, on Eden Project: Morecambe, what assessment has been made by the his Department of whether the Eden Project North is able to provide its side of the...
An assessment of match funding was undertaken as part of the original business case. We remain in regular contact with the council, who keep the Department updated on the latest developments, including progress on the project’s funding position. However, given the commercially sensitive nature of the match funding arrangements, including the sources involved, it would not be appropriate to provide further detail at this stage.
To ask the Secretary of State for Housing, Communities and Local Government, with reference to the answer of 19 March 2026 to Question 120470 on Eden Project: Morecambe, how much funding will be given to the Eden Project Morecombe; and over what period.
To ask the Secretary of State for Housing, Communities and Local Government, with reference to the answer of 19 March 2026 to Question 120470 on Eden Project: Morecambe, how much funding will be given to the Eden Project Morecombe; and over what period.
Eden Project: Morecambe have been allocated £50 million via the Local Regeneration Fund. Funding is paid to Lancaster City Council as sponsors of the Eden Project Morecambe and must be spent by March 2028.
To ask the Secretary of State for Energy Security and Net Zero, if he will make an assessment of the economic impact of the extension to the deadline for the decision on granting a Development Consent Order to the Morgan-Morecambe transmission assets.
To ask the Secretary of State for Energy Security and Net Zero, if he will make an assessment of the economic impact of the extension to the deadline for the decision on granting a Development Consent Order to the Morgan-Morecambe transmission assets.
The application for development consent was assessed in the usual way against all relevant planning considerations. An extension to the deadline for deciding the application was announced on 14 May by written ministerial statement to Parliament. It would not be appropriate to comment further while the case remains live.
To ask the Secretary of State for Housing, Communities and Local Government, whether his Department has made an assessment of the potential impact of local government restructuring on the (a) administration and (b) viability of the Eden Project Morecambe.
To ask the Secretary of State for Housing, Communities and Local Government, whether his Department has made an assessment of the potential impact of local government restructuring on the (a) administration and (b) viability of the Eden Project Morecambe.
During the local government reorganisation process, it is expected that councils continue to deliver their services and duties as usual until reorganisation is complete. The proposed restructuring of local government has not been raised, in discussion between officials and the project, as having an impact on delivery. Following the completion of reorganisation, commitments undertaken by existing councils will become the responsibility of any new unitary authorities.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 20 January 2026 to Question 105396 on Eden Project: Morecambe, whether he has had discussions with representatives from (a) Lancaster City Council and (b) any other sponsors of the Eden Project on (i)...
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 20 January 2026 to Question 105396 on Eden Project: Morecambe, whether he has had discussions with representatives from (a) Lancaster City Council and (b) any other sponsors of the Eden Project on (i)...
I have had no engagement. My officials have as part of regular monitoring as per the answer given to Question UIN 120470 on 19 March 2026.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the answer of 20 January 2026, to Question 105396, on Eden Project: Morecambe, what assessment has his department made for the reasons to the scaling back of the Eden Project since July 2024.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the answer of 20 January 2026, to Question 105396, on Eden Project: Morecambe, what assessment has his department made for the reasons to the scaling back of the Eden Project since July 2024.
Since July 2024 the Eden Project Morecambe team has continued design work. An update on potential options for the development, including their size and scale, was presented to MHCLG in March 2025. These options were subject to ongoing community conversations. In September 2025, the department launched the Local Regeneration Fund which provided certainty of funding and flexibility to Local Authorities, including Lancaster City Council as sponsors of the Eden Project Morecambe. The Eden Project Morecambe team submitted a planning application for their preferred option on the 15th of October 2025. The planning application proposal has been approved, subject to S106 approval and 6 week judicial review period.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 7 November 2025 to Question 87114 on Eden Project: Morecambe, what data his Department holds on any changes made to the scale and size of the proposed Eden Project development since July 2024.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 7 November 2025 to Question 87114 on Eden Project: Morecambe, what data his Department holds on any changes made to the scale and size of the proposed Eden Project development since July 2024.
Since July 2024 the Eden Project: Morecambe team have continued design work.
An update on potential options for the development, including their size and scale, was presented to MHCLG in March 2025. These options were subject to ongoing community conversations.
In September 2025, the department launched the Local Regeneration Fund which provided certainty of funding and flexibility to Local Authorities, including Lancaster City Council as sponsors of the Eden Project Morecambe.
The Eden Project: Morecambe team submitted a planning application for their preferred option on the 15th of October 2025. The planning application proposal is currently out for consultation, ending 23rd January.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 30 October 2025 to Question 84636 on Eden Project: Morecombe, if he will publish the Memorandum of Understanding; and what proportion of the £50 million of funding is conditional on matched funding.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 30 October 2025 to Question 84636 on Eden Project: Morecombe, if he will publish the Memorandum of Understanding; and what proportion of the £50 million of funding is conditional on matched funding.
We have no plans to publish the Memorandum of Understanding signed on 19th November 2024 as the project information is published by the local authority responsible for the project. Available on gov.uk here.
The grant funding provided to the project is not conditional on match funding; however, the Local Authority is responsible for securing the additional funds required to deliver the benefits for which the funding was granted.
To ask the Secretary of State for Housing, Communities and Local Government, whether any changes have been made to the (a) government funding and (b) funding profile for the Eden North project following the decision to cancel the Levelling Up Fund.
To ask the Secretary of State for Housing, Communities and Local Government, whether any changes have been made to the (a) government funding and (b) funding profile for the Eden North project following the decision to cancel the Levelling Up Fund.
The MHCLG Levelling Up Fund, Town Deals, and Simplification Pathfinder Pilot have been consolidated into the Local Regeneration Fund.
There have been no changes to government funding and no changes to the funding profile, since the MoU was fully signed in November 2024.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 13 October 2025 to Question 77627 on Eden Project: Morecambe, whether he plans to allocate £100 million to the Eden Project North.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 13 October 2025 to Question 77627 on Eden Project: Morecambe, whether he plans to allocate £100 million to the Eden Project North.
The department has committed £50 million towards the total project cost of £100 million for Eden Project Morecambe. The Memorandum of Understanding for the full £50 million grant, was fully signed on 19 November 2024.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 13 October 2025 to Question 77627 on Eden Project: Morecambe, what the (a) £6.3 million and (b) £10.8 million will be spent on.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 13 October 2025 to Question 77627 on Eden Project: Morecambe, what the (a) £6.3 million and (b) £10.8 million will be spent on.
The £6.3 million and the £10.8 million referenced in the answer given to Question UIN 77627 is for the technical building / design work and site investigation works that will then lead to enabling and construction work on site.
This is in line with the information provided by Lancashire City Council in their Q4 monitoring return, submitted 16 May 2025.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 25 February 2025 to Question 33500 on Eden Project: Morecambe, how much government funding has been spent on supporting the project to date; and on what date were the funds released.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 25 February 2025 to Question 33500 on Eden Project: Morecambe, how much government funding has been spent on supporting the project to date; and on what date were the funds released.
The MHCLG Levelling Up Fund, Town Deals, and Simplification Pathfinder Pilot have been consolidated into the Local Regeneration Fund. This new fund will give local authorities more local control, reducing unnecessary administrative burdens and maximising freedom and flexibility to get on with delivery.
As of March 2025, £6,336,514 has been released to support the Eden project: Morecambe. Department officials contacted Lancaster City Council on 11 September to confirm details for a payment to cover forecasted activity for the remainder of the 2025/26 financial year. A further payment, of £10,814,457, is due to be paid in September 2025.
Q10
.
Mr Andrew Snowden (Fylde) (Con):
Whether or not people agree with the Prime Minister’s net zero targets, he must agree that he will not achieve those targets without taking people with him. The cable corridor and substation for the Morgan and Morecambe offshore wind farm is one of the most objected to national energy infrastructure projects in the country. What is angering me and thousands of others is that there is a perfect alternative cabling route further up the coast that would bring local economic benefit, would be more cost-effective as a whole lifecycle project and could connect to existing national grid infrastructure, but no one is listening. Will the Prime Minister now listen, pause the planning inquiry for the existing application and ask the Department for Energy Security and Net Zero to consider and cost the alternative route to avoid untold devastation to our coastline and countryside?
Q10
.
Mr Andrew Snowden (Fylde) (Con):
Whether or not people agree with the Prime Minister’s net zero targets, he must agree that he will not achieve those targets without taking people with him. The cable corridor and substation for the Morgan and Morecambe offshore wind farm is one of the most objected to national energy infrastructure projects in the country. What is angering me and thousands of others is that there is a perfect alternative cabling route further up the coast that would bring local economic benefit, would be more cost-effective as a whole lifecycle project and could connect to existing national grid infrastructure, but no one is listening. Will the Prime Minister now listen, pause the planning inquiry for the existing application and ask the Department for Energy Security and Net Zero to consider and cost the alternative route to avoid untold devastation to our coastline and countryside?
As the hon. Gentleman will know, the Secretary of State for Energy Security and Net Zero is going through a quasi-judicial exercise, and I am therefore limited in what I can say. Let me do the best I can within those constraints. The project is going through its examination, where interested parties can and should put forward their views on the application. More broadly, as we drive forward renewable projects, the planning process is designed to ensure that impacts are carefully considered.
As the hon. Gentleman will know, the Secretary of State for Energy Security and Net Zero is going through a quasi-judicial exercise, and I am therefore limited in what I can say. Let me do the best I can within those constraints. The project is going through its examination, where interested parties can and should put forward their views on the application. More broadly, as we drive forward renewable projects, the planning process is designed to ensure that impacts are carefully considered.
As the hon. Gentleman will know, the Secretary of State for Energy Security and Net Zero is going through a quasi-judicial exercise, and I am therefore limited in what I can say. Let me do the best I can within those constraints. The project is going through its examination, where interested parties can and should put forward their views on the application. More broadly, as we drive forward renewable projects, the planning process is designed to ensure that impacts are carefully considered.
Q10
.
Mr Andrew Snowden (Fylde) (Con):
Whether or not people agree with the Prime Minister’s net zero targets, he must agree that he will not achieve those targets without taking people with him. The cable corridor and substation for the Morgan and Morecambe offshore wind farm is one of the most objected to national energy infrastructure projects in the country. What is angering me and thousands of others is that there is a perfect alternative cabling route further up the coast that would bring local economic benefit, would be more cost-effective as a whole lifecycle project and could connect to existing national grid infrastructure, but no one is listening. Will the Prime Minister now listen, pause the planning inquiry for the existing application and ask the Department for Energy Security and Net Zero to consider and cost the alternative route to avoid untold devastation to our coastline and countryside?
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025 to Question 23790 on Eden Project: Morecambe, when the full business case was (a) submitted to and (b) confirmed by her Department.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025 to Question 23790 on Eden Project: Morecambe, when the full business case was (a) submitted to and (b) confirmed by her Department.
The final full business case for the Levelling Up Fund (LUF) Round 2 project “Eden Project North” was received by the department on the 23 September 2024. A memorandum of understanding was issued to Lancaster City Council on the 18 November 2024 and signed by the department on the 19 November 2024.
It is expected that this project will have full match funding of £50 million making the total LUF project cost £100 million.
I can confirm that all allocated funding will be available from Quarter one of 2026.
The latest delivery milestones timetable is for each milestones including dates is set out below.
Full design stage – (RIBA 2-4) March 25 - October 26
Initial enabling works during design - August 2025 - November 2025
Main site enabling works commences - March 2026 - July 2026
Main construction commences - March 2026 - July 2028
Main Construction Practical Completion – July 2028 - August 2028
Operational Readiness, Activation and Transition – May 2028 - October 2028
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025, to Question 23790, on Eden Project: Morecambe, whether the allocated funding will be available from Quarter one of 2026.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025, to Question 23790, on Eden Project: Morecambe, whether the allocated funding will be available from Quarter one of 2026.
The final full business case for the Levelling Up Fund (LUF) Round 2 project “Eden Project North” was received by the department on the 23 September 2024. A memorandum of understanding was issued to Lancaster City Council on the 18 November 2024 and signed by the department on the 19 November 2024.
It is expected that this project will have full match funding of £50 million making the total LUF project cost £100 million.
I can confirm that all allocated funding will be available from Quarter one of 2026.
The latest delivery milestones timetable is for each milestones including dates is set out below.
Full design stage – (RIBA 2-4) March 25 - October 26
Initial enabling works during design - August 2025 - November 2025
Main site enabling works commences - March 2026 - July 2026
Main construction commences - March 2026 - July 2028
Main Construction Practical Completion – July 2028 - August 2028
Operational Readiness, Activation and Transition – May 2028 - October 2028
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025, to Question 23791, on Eden Project: Morecambe, what the total cost of the project is.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025, to Question 23791, on Eden Project: Morecambe, what the total cost of the project is.
The final full business case for the Levelling Up Fund (LUF) Round 2 project “Eden Project North” was received by the department on the 23 September 2024. A memorandum of understanding was issued to Lancaster City Council on the 18 November 2024 and signed by the department on the 19 November 2024.
It is expected that this project will have full match funding of £50 million making the total LUF project cost £100 million.
I can confirm that all allocated funding will be available from Quarter one of 2026.
The latest delivery milestones timetable is for each milestones including dates is set out below.
Full design stage – (RIBA 2-4) March 25 - October 26
Initial enabling works during design - August 2025 - November 2025
Main site enabling works commences - March 2026 - July 2026
Main construction commences - March 2026 - July 2028
Main Construction Practical Completion – July 2028 - August 2028
Operational Readiness, Activation and Transition – May 2028 - October 2028
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025, to Question 23789, on Eden Project: Morecambe, what the latest delivery milestones timetable is for each milestone including dates.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025, to Question 23789, on Eden Project: Morecambe, what the latest delivery milestones timetable is for each milestone including dates.
The final full business case for the Levelling Up Fund (LUF) Round 2 project “Eden Project North” was received by the department on the 23 September 2024. A memorandum of understanding was issued to Lancaster City Council on the 18 November 2024 and signed by the department on the 19 November 2024.
It is expected that this project will have full match funding of £50 million making the total LUF project cost £100 million.
I can confirm that all allocated funding will be available from Quarter one of 2026.
The latest delivery milestones timetable is for each milestones including dates is set out below.
Full design stage – (RIBA 2-4) March 25 - October 26
Initial enabling works during design - August 2025 - November 2025
Main site enabling works commences - March 2026 - July 2026
Main construction commences - March 2026 - July 2028
Main Construction Practical Completion – July 2028 - August 2028
Operational Readiness, Activation and Transition – May 2028 - October 2028
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025 to Question 23789 on the Eden Project: Morecambe, what estimate she has been made of any change in the (a) build and (b) operating costs of the project in light...
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025 to Question 23789 on the Eden Project: Morecambe, what estimate she has been made of any change in the (a) build and (b) operating costs of the project in light...
The final full business case for the Levelling Up Fund (LUF) Round 2 project “Eden Project North” was received by the department on the 23 September 2024. A memorandum of understanding was issued to Lancaster City Council on the 18 November 2024 and signed by the department on the 19 November 2024.
It is expected that this project will have full match funding of £50 million making the total LUF project cost £100 million.
I can confirm that all allocated funding will be available from Quarter one of 2026.
The latest delivery milestones timetable is for each milestones including dates is set out below.
Full design stage – (RIBA 2-4) March 25 - October 26
Initial enabling works during design - August 2025 - November 2025
Main site enabling works commences - March 2026 - July 2026
Main construction commences - March 2026 - July 2028
Main Construction Practical Completion – July 2028 - August 2028
Operational Readiness, Activation and Transition – May 2028 - October 2028
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025 to Question 23789 on Eden Project: Morecambe, when her Department expects the project to be (a) completed and (b) open to visitors.
To ask the Secretary of State for Housing, Communities and Local Government, pursuant to the Answer of 23 January 2025 to Question 23789 on Eden Project: Morecambe, when her Department expects the project to be (a) completed and (b) open to visitors.
The final full business case for the Levelling Up Fund (LUF) Round 2 project “Eden Project North” was received by the department on the 23 September 2024. A memorandum of understanding was issued to Lancaster City Council on the 18 November 2024 and signed by the department on the 19 November 2024.
It is expected that this project will have full match funding of £50 million making the total LUF project cost £100 million.
I can confirm that all allocated funding will be available from Quarter one of 2026.
The latest delivery milestones timetable is for each milestones including dates is set out below.
Full design stage – (RIBA 2-4) March 25 - October 26
Initial enabling works during design - August 2025 - November 2025
Main site enabling works commences - March 2026 - July 2026
Main construction commences - March 2026 - July 2028
Main Construction Practical Completion – July 2028 - August 2028
Operational Readiness, Activation and Transition – May 2028 - October 2028