Skip to main content

Written question asked by Gary Streeter (Conservative) on Monday, 28 February 2005, in the House of Commons. It was due for an answer on Thursday, 10 March 2005. It was answered by Adam Ingram (Labour) on Thursday, 10 March 2005 on behalf of the Ministry of Defence.


Ministry of Defence

Question
To ask the Secretary of State for Defence, on what basis the contracts to refit HMS Edinburgh and HMS Ark Royal were awarded to Rosyth Dockyard; and what the cost to public funds is of each contract; whether his Department always accepts the most competitive tender for the refitting of surface ships.
Answer

Mr. Streeter: To ask the Secretary of State for Defence (1) on what basis the contracts to refit HMS Edinburgh and HMS Ark Royal were awarded to Rosyth Dockyard; and what the cost to public funds is of each contract; [219714] (2) whether his Department always accepts the most competitive tender for the refitting of surface ships. [219716] Mr. Ingram: Contracts for the refitting of surface ships, including those for HMS Edinburgh and HMS Ark Royal, are awarded following open competitions. Royal Navy surface ship work is competed fairly and all tenders within the same competition are assessed against identical criteria, such as technical and commercial compliance, partnering proposals and price. The outcome is judged on overall value for money against these criteria. The estimated cost for the refits of HMS Edinburgh and HMS Ark Royal, including the Ministry of Defence supplied materials, are around £20 million and £55 million respectively.


Secondary information

Type
Written question
Reference
431 c1995W;431 c1987W; 219714;219716
Session
2004-05
Subjects
Contracts Costs Repairs and maintenance Warships Rosyth Dockyard HMS Ark Royal HMS Edinburgh
Contains statistics
Yes
Link
View this Written question on www.publications.parliament.uk