Energy: Dounreay Fast Breeder Reactor

Question
What was the total cost of building and operating the fast breeder reactor at Dounreay during its operational life; how long will it take to decommission the plant; and at what total cost.
Answer

The prototype fast reactor was estimated upon completion in 1974 to have cost approximately £40 million. Annual operating costs for the fast reactor programme averaged £50 million per year. The PFR closed in 1994 (these costs are quoted in cash of the year). The most recent estimate published in the site lifetime plan for the cost of decommissioning the PFR is in the region of £300 million. Decommissioning is due to be complete by 2033.


Secondary information

Type
Written question
Reference
685 c208WA; 7705
Session
2005-06
Subjects
Decommissioning Costs Construction Nuclear power stations Dounreay Fast reactors Operating costs
Contains statistics
Yes
Link
View this Written question on www.publications.parliament.uk