Written question asked by Lord Storey (Liberal Democrat), in the House of Lords. It was answered by Earl Attlee (Conservative) on Monday, 21 November 2011.
Transport: Trams
- Question
- To ask Her Majesty’s Government which tram and light rail projects they have supported financially in the past five years; how much they have spent on each of those projects; how far each of those projects has been developed; and what are the plans for those projects that have yet to be completed.
- Answer
-
The information is as follows:
Scheme Name Total Capital Funding provided to date (£m) Current position Tyne and Wear Metro Gating and Ticketing 7.4 Under Construction Blackpool Tram Upgrade 65.2 Under Construction Manchester Metrolink Phase 3a 242.2 Under Construction Manchester Metrolink – Ashton & E Didsbury Extensions 60.9 Under Construction Manchester Metrolink Phase 1 Renewals 46.8 Under Construction The department has provided both operating subsidy and the following funding to the Tyne and Wear Metro system in each of the past five financial years. The revenue support was mainly to contribute to the operational cost of the Metro. The capital grant was for capital renewals and the increase in this in the last three years relates to the Metro reinvigoration upgrade programme.
Revenue support Capital grant 2006-07 £18.057m £4.305m 2007-08 £20.779m £4.391m 2008-09 £22.681m £7.548m 2009-10 £23.123m £21.495m 2010-11 £25.300m £35.789m 2011-12 (to date) £11.066m £14.435m The Government have provided to date £164 million of million of annuity support for the first phase of the Nottingham Express Transport system. The Government have also announced they will fund extensions to both the Nottingham and Midland Metro light rail systems, subject to successful completion of the final approval stages and procurement. Neither of these schemes has reached the construction stage. The Government are also currently considering a bid for additional vehicles on the Sheffield Supertram system. In addition Transport for London has also funded improvements to the Docklands Light Railway and Croydon Tramlink systems using funding provided by Government through its block grant. The Edinburgh Tram scheme, currently under construction, is being part-funded by the Scottish Government.
Secondary information
- Type
- Written question
- Reference
- 13311; 732 c213-4WA
- Session
- 2010-12
- Related items
- Subjects
- Expenditure Rapid transit systems Trams
- Contains statistics
- Yes
- Link
- View this Written question on www.publications.parliament.uk
Librarians' tools
- Timestamp
- 2022-04-26 12:18:54 +0100
- URI
- http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1653596
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1653596
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1653596