Written question asked by Baroness Hayman of Ullock (Labour) on Thursday, 25 June 2015, in the House of Commons. It was due for an answer on Tuesday, 30 June 2015 (named day). A holding answer was provided on Tuesday, 30 June 2015. A substantive answer was provided by Andrea Leadsom (Conservative) on Thursday, 2 July 2015 on behalf of the Department of Energy and Climate Change.


Magnox Reactors: Decommissioning

Question

To ask the Secretary of State for Energy and Climate Change, how long it will take to complete decommissioning of Magnox sites on current annual expenditure.

Answer

Under current plans, all Magnox sites will be rendered passively safe with the reactor structures in safe stores by 2028. Final clearance of the sites is planned from around 2080 onwards. End dates for the Magnox sites are published in the Nuclear Decommissioning Authority’s Strategy document. Annual expenditure at the Magnox sites is forecast to vary significantly over the duration of the decommissioning programme and is expected to decrease as the reactor structures move into safe store.


Secondary information

Type
Written question
Reference
4291
Session
2015-16
Subjects
Decommissioning Magnox reactors
Contains statistics
Yes
Link
View this Written question on www.parliament.uk