Written question asked by Iain Wright (Labour) on Wednesday, 26 October 2016, in the House of Commons. It was due for an answer on Friday, 28 October 2016. It was answered by Jesse Norman (Conservative) on Thursday, 3 November 2016 on behalf of the Department for Business, Energy and Industrial Strategy.
Magnox Reactors
- Question
-
To ask the Secretary of State for Business, Energy and Industrial Strategy, what the reasons are for the increase in costs of £1.6 billion by Cavendish Fluor Partnership for the clean-up project for 12 Magnox reactors.
- Answer
-
The Nuclear Decommissioning Authority’s (NDA’s) contract with Cavendish Fluor Partnership (CFP) contains a provision to allow for a period of consolidation between the NDA and CFP, ensuring the contract is in line with delivery on the ground.
The NDA’s consolidation process has not yet concluded and therefore it is not appropriate to comment on this figure.
Secondary information
- Type
- Written question
- Reference
- 50410
- Session
- 2016-17
- Subjects
- Decommissioning Costs Magnox reactors
- Contains statistics
- Yes
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2016-11-03 18:30:06 +0000
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/commons/2016-17/50410
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/commons/2016-17/50410
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/commons/2016-17/50410