Written question asked by Lord Berkeley (Labour) on Monday, 29 February 2016, in the House of Lords. It was due for an answer on Monday, 14 March 2016. It was answered by Lord Ahmad of Wimbledon (Conservative) on Wednesday, 9 March 2016 on behalf of the Department for Transport.
High Speed 2 Line
- Question
-
To ask Her Majesty’s Government, further to the Written Answer by Lord Ahmad of Wimbledon on 10 February (HL5652), what (1) proportion, and (2) volume, of excavated spoil from each of the HS2 Phase 1 construction sites will be transported from them by (a) rail, (b) road, and (c) river.
- Answer
-
Excavated material arising from the construction of Phase One of HS2 will be transported along the construction corridor (site haul) where it is reasonably practicable to do so. Where that is not possible, or for movement along longer distances, the material will be transported by public highway, along designated routes. Where reasonably practicable, rail has been considered for the transportation of large quantities of excavated material over long distances. There are currently no plans to move any of the excavated material by river.
The approximate quantities and relative proportion of each of these transportation methods, allocated to broad sections of the proposed route is set out in the table below. These figures reflect the assumptions reported in the Environmental Statement deposited alongside the Phase One Bill and, as such, are a plausible worst case in terms of both total volume of excavated material and proportion transport by highway and rail. The project has made a commitment to maximise the amount of excavated material transported by rail and are working to increase the proportion transport by rail and decrease the proportion transported by highway wherever reasonably practicable.
(All figures are in million tons and movements may include multiple handling)
Site Haul
Public Highway Haul
Rail Haul
Central London & Metropolitan area
16.9 (56%)
4 (13%)
9.46 (31%)
Buckinghamshire Northants & Warwickshire Country areas
72.4 (80%)
17.9 (20%)
- (0%)
West Midlands Metropolitan area
29.9 (61%)
18.9 (39%)
- (0%)
Total Phase One Routewide
119.2 (70%)
40.8 (24%)
9.46 (6%)
Secondary information
- Type
- Written question
- Reference
- HL6509
- Session
- 2015-16
- Related items
- Subjects
- Construction Excavation Transport High Speed 2 line Waste
- Contains statistics
- Yes
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2025-07-29 10:44:32 +0100
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/lords/2015-16/HL6509
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/lords/2015-16/HL6509
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/lords/2015-16/HL6509