Written question asked by Lord Berkeley (Labour) on Thursday, 15 December 2016, in the House of Lords. It was due for an answer on Tuesday, 3 January 2017. It was answered by Lord Ahmad of Wimbledon (Conservative) on Wednesday, 21 December 2016 on behalf of the Department for Transport.


High Speed 2 Line

Question

To ask Her Majesty’s Government whether they are still committed to the £55.7 billion allocated in the 2015 Spending Review for HS2 and, if so, what are the budgets for (1) purchase of rolling stock, and (2) all development, construction and commissioning work for Phase 1, Phase 2A and Phase 2B.

Answer

Spending Review 2015 set a long term funding envelope for HS2 of £55.7 billion in 2015 prices. The Government remains committed to delivering HS2 within this funding envelope. A breakdown of the funding envelope, with and without contingency, has been provided below:

£ billion, 2015 Prices

Phase One

Phase 2a

Phase 2b

Rolling Stock

Total

Without contingency

18.0

2.7

14.7

5.4

40.8

With contingency

24.3

3.7

20.7

7.0

55.7


Secondary information

Type
Written question
Reference
HL4189
Session
2016-17
Related items
High Speed 2 Line
Wednesday, 26 April 2017
Written questions
House of Lords
Subjects
Construction Finance Procurement Rolling stock High Speed 2 line
Contains statistics
Yes
Link
View this Written question on www.parliament.uk