Written question asked by Lord Berkeley (Labour) on Monday, 27 March 2017, in the House of Lords. It was due for an answer on Monday, 10 April 2017. It was answered by Lord Ahmad of Wimbledon (Conservative) on Friday, 7 April 2017 on behalf of the Department for Transport.


High Speed 2 Line

Question

To ask Her Majesty’s Government, further to the Written Answer by Lord Ahmad of Wimbledon on 21 March (HL6081), what is their estimate of the cost of constructing the Handsacre connection to the West Coast Main Line compared with a straight connection to HS2 Phase 2A towards Crewe.

Answer

The total budget for High Speed 2 is £55.7bn. HS2 Ltd is currently procuring contractors to deliver the first Phase of HS2. The Department for Transport does not release details of the estimated cost of constructing individual components of the scheme as this information is commercially sensitive.


Secondary information

Type
Written question
Reference
HL6300
Session
2016-17
Related items
High Speed 2 Line
Thursday, 23 March 2017
Written questions
House of Lords
Subjects
Costs Construction West Coast main line High Speed 2 line
Contains statistics
Yes
Link
View this Written question on www.parliament.uk