Skip to main content

Written question asked by Lord Berkeley (Labour) on Tuesday, 15 November 2022, in the House of Lords. It was due for an answer on Tuesday, 29 November 2022. It was answered by Baroness Goldie (Conservative) on Tuesday, 29 November 2022 on behalf of the Ministry of Defence.


Warships: River Clyde

Question

To ask His Majesty's Government what steps they will take to ensure that the five new warships to be built on the Clyde are not subject to delay.

Answer

The Type 26 Batch 2 contract is structured to motivate both the Ministry of Defence and BAE Systems to deliver a successful outcome, with both parties sharing in the pain and gain in delivering the programme, ensuring value for public money and protecting the taxpayers from any project overrun costs.

The Batch 2 contract introduces further investment in BAE Systems' shipbuilding facilities on the Clyde, as demonstrated by the submission of planning application for a new Shipbuilding Hall at Govan, which will allow two frigates to be built under cover simultaneously and enable the ships to be built faster, improving the efficiency in the programme and expanding the facilities for future work at the yard.


Secondary information

Type
Written question
Reference
HL3406
Session
2022-23
Subjects
Shipbuilding Warships River Clyde
Link
View this Written question on www.parliament.uk