Written question asked by Lord Berkeley (Labour) on Thursday, 29 January 2026, in the House of Lords. It was due for an answer on Thursday, 12 February 2026. It was answered by Lord Hendy of Richmond Hill (Labour) on Wednesday, 11 February 2026 on behalf of the Department for Transport.
High Speed 2 Line: Tunnels
- Question
-
To ask His Majesty's Government what the names of the six major rail tunnel and road milestones completed ahead of schedule in 2025 are, as cited by Rt Hon Darren Jones MP in their announcement on 27 January of the start of boring work on the tunnels between Old Oak Common and Euston.
- Answer
-
The six major rail tunnel and road milestones completed ahead of schedule in 2025 are as follows:
Milestone
Planned Date
Actual Date
A46 – completion of structure – road re-opened
May-25
Apr-25
Bromford tunnel – tunnel boring machine (TBM) 2 (Elizabeth) breakthrough
Dec-25
Oct-25
Station Road alignment – installation of precast beams on HS2 and National Rail overbridges (Calvert)
Oct-25
Aug-25
Section 5 structure finish for Greatworth Green tunnel
Jul-25
May-25
Euston tunnels downline TBM – assemble / install tail skin and screw conveyor
Apr-25
Mar-25
Northolt tunnels east down line tunnel boring machine extracted at Green Park Way vent shaft
Nov-25
Aug-25
Secondary information
- Type
- Written question
- Reference
- HL14091
- Session
- 2024-26
- Subjects
- Construction High Speed 2 line Tunnels Old Oak Common Station Euston Station
- Contains statistics
- Yes
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2026-02-11 17:27:24 +0000
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/lords/2024-26/HL14091
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/lords/2024-26/HL14091
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/lords/2024-26/HL14091