Written question asked by Lord Berkeley (Labour) on Thursday, 23 February 2017, in the House of Lords. It was due for an answer on Thursday, 9 March 2017. It was answered by Lord Ahmad of Wimbledon (Conservative) on Thursday, 9 March 2017 on behalf of the Department for Transport.


High Speed 2 Line

Question

To ask Her Majesty’s Government how long they expect journey times to be for HS2 trains between London and (1) Crewe, (2) Edinburgh, and (3) Glasgow, when Phases 1 and 2A are completed, compared with the present Pendolino services, and whether they have estimated the time saving that would be gained if the HS2 trains incorporated a tilting mechanism and so could be used on the West Coast Main Line North of Crewe; and if so, what is that time saving.

Original answer

The proposed HS2 rolling stock tender specification does not preclude a bidder offering a tilting train solution. However, no tilting trains currently operate faster than 250km/h. HS2 Ltd assumes that tilting rolling stock could achieve a maximum operating speed on the high speed network of 300km/h rather than 360km/h for non-tilting rolling stock. This lower maximum operating speed would increase journey times on the dedicated HS2 network and could reduce network capacity. HS2 Ltd has assumed a number of minor line speed improvements on the northern West Coast Main Line for non-tilting rolling stock.

HS2 will not serve Edinburgh until Phase 2B opens. Existing and projected estimated journey times from London Euston are as follows:

Crewe

Glasgow

WCML Pendolino

1h30

4h17

Phase 1 non-tilt

1h08

4h00

Phase 1 tilt

Approx 1h11

Approx 4h00

Phase 2A non-tilt

0h55

3h48

Phase 2A tilt

Approx 1h01

Approx 3h51

The answer was corrected by Lord Ahmad of Wimbledon (Conservative)

on Thursday, 9 March 2017 on behalf of the Department for Transport.

Corrected answer

The proposed HS2 rolling stock tender specification does not preclude a bidder offering a tilting train solution. However, no tilting trains currently operate faster than 250km/h. HS2 Ltd assumes that tilting rolling stock could achieve a maximum operating speed on the high speed network of 300km/h rather than 360km/h for non-tilting rolling stock. This lower maximum operating speed would increase journey times on the dedicated HS2 network and could reduce network capacity. HS2 Ltd has assumed a number of minor line speed improvements on the northern West Coast Main Line for non-tilting rolling stock.

HS2 will not serve Edinburgh until Phase 2B opens. Existing and projected estimated journey times from London Euston are as follows:

Crewe

Glasgow

WCML Pendolino

1hr30

4hr17

Phase 1 non-tilt

1h08

4h00

Phase 1 tilt

Approx 1hr11

Approx 4h00

Phase 2A non-tilt

0h55

3h48

Phase 2A tilt

Approx1h01

Approx 3h51

Crewe

Glasgow

WCML Pendolino

1h30

4h17

Phase 1 non-tilt

1h08

4h00

Phase 1 tilt

Approx 1h11

Approx 4h00

Phase 2A non-tilt

0h55

3h48

Phase 2A tilt

Approx 1h01

Approx 3h51


Secondary information

Type
Written question
Reference
HL5562
Session
2016-17
Related items
High Speed 2 Line
Thursday, 23 March 2017
Written questions
House of Lords
High Speed 2 Line
Thursday, 23 March 2017
Written questions
House of Lords
West Coast Main Line
Thursday, 23 March 2017
Written questions
House of Lords
Subjects
Design Trains West Coast main line High Speed 2 line
Contains statistics
Yes
Link
View this Written question on www.parliament.uk