Proceeding contribution from Tom Harris (Labour) in the House of Commons on Thursday, 13 December 2007. It occurred during Debate on bill on Crossrail Bill.


Crossrail Bill

The clause in question is not for when something goes wrong; it is there to be flexible enough to accommodate unforeseen circumstances. At this moment it is not possible to make a list of all temporary and permanent easements and the uses to which they would be put. I am sure that the hon. Gentleman will understand why I do not want to speculate about any hypothetical effect of the Planning Bill. Given the examples that I have just cited and my explanation, I hope that the hon. Member for Wimbledon, being a sensible and reasonable chap, will agree to withdraw amendment No. 2. I turn to amendment No. 3. Clause 10 deems planning permission to be granted for two different categories of works. First, the scheduled works listed in schedule 1 have to be built within their respective limits of deviation. Secondly, as long as other non-scheduled works fall within the scope of the various environmental assessments accompanying the Bill, they can be built anywhere within the limit of deviation or the limit of land to be acquired or used. In addition, safeguarding work to buildings necessary or expedient in connection with the works can be carried out outside these limits, but within a specified distance of the works in relation to which the protection is provided—50 m where the work relates to an underground railway and 35 m in other circumstances. The geographical extent of the works and the planning permission granted by the Bill is therefore well known and transparent. For example, the main railway and running tunnels are scheduled works, as are all the new stations to be built in the central section. Planning permission for those works is therefore granted within their limits of deviation. However, some works are not scheduled works and so get planning permission only if they have been environmentally assessed. These include ancillary works such as station alterations and electrification works on the existing national rail networks within the limits of land to be acquired or used, and protective works to buildings outside those limits. I am therefore satisfied that the scope of the deemed planning permission is limited to the works that are reasonably required to enable Crossrail to be built. Furthermore, all works are subject to the detailed consent regime set out in schedule 7, and stakeholders will have had the opportunity to consider detailed information about the likely environmental impacts of all the works for which deemed planning permission is proposed to be granted, and if necessary to petition. The hon. Gentleman’s amendment would require separate planning permission to be sought for any works authorised by the Bill that are not scheduled works and fall outside the limits of deviation of the works. That would, as I have indicated, affect a wide category of works, including unscheduled works that lie within the limits of the Bill. The effect of requiring separate planning permission to be sought for such works would be to undermine the very purpose of the Bill—that is, to obtain deemed planning permission for the works reasonably required to enable Crossrail to be built, where they have had appropriate environmental assessment. It would expose the project to the risk of severe delays as local authorities considered applications for these works under the 1990 Act regime, including possibly the holding of public inquiries. On the basis of that explanation, I invite the hon. Gentleman to withdraw his amendment. If for no other reason, I hope that he accepts that undue delay to the schedule for the construction of Crossrail would result in added costs. If he is so concerned about added costs of the scheme and transparency in funding it, I hope that he will accept that his amendment would add nothing to the demands to keep the costs of Crossrail down.


Secondary information

Type
Proceeding contribution
Reference
469 c531-2 
Session
2007-08
Chamber / Committee
House of Commons chamber
Subjects
Access Disclosure of information Compensation Compulsory purchase Construction Elizabeth line Crossrail Finance Land Environment Infrastructure Freight Planning permission Railway stations Railways Railway network Reading (Berkshire) Underground railways Regeneration Woolwich Maidenhead Office of Rail Regulation
Legislation
Crossrail Bill 2004/05 to 2005-06 to 2006-07 to 2007-08
Link
View this Proceeding contribution on www.publications.parliament.uk