Written question asked by Antoinette Sandbach (Conservative) on Tuesday, 12 September 2017, in the House of Commons. It was due for an answer on Thursday, 14 September 2017. It was answered by Paul Maynard (Conservative) on Tuesday, 19 September 2017 on behalf of the Department for Transport.


High Speed 2 Line: Eddisbury

Question

To ask the Secretary of State for Transport, how many environmental surveys have been conducted on the proposed route of the second phase of High Speed 2 through Eddisbury; and how many land access agreements have been signed between HS2 Ltd and property owners in Eddisbury.

Answer

As of the week ending 8-9-17, approximately 217 environmental surveys had been recorded in and around the Eddisbury area.

To date, HS2 Ltd has recorded a total of 90 land access licences as having been agreed entirely or partially within Eddisbury. The corresponding number for those entirely within Eddisbury is 52.

These figures are subject to change.


Secondary information

Type
Written question
Reference
10295
Session
2017-19
Subjects
Access Land Surveys Eddisbury High Speed 2 line
Contains statistics
Yes
Link
View this Written question on www.parliament.uk