Written question asked by Antoinette Sandbach (Conservative) on Tuesday, 12 September 2017, in the House of Commons. It was due for an answer on Thursday, 14 September 2017. It was answered by Paul Maynard (Conservative) on Tuesday, 19 September 2017 on behalf of the Department for Transport.
High Speed 2 Line: Eddisbury
- Question
-
To ask the Secretary of State for Transport, how many environmental surveys have been conducted on the proposed route of the second phase of High Speed 2 through Eddisbury; and how many land access agreements have been signed between HS2 Ltd and property owners in Eddisbury.
- Answer
-
As of the week ending 8-9-17, approximately 217 environmental surveys had been recorded in and around the Eddisbury area.
To date, HS2 Ltd has recorded a total of 90 land access licences as having been agreed entirely or partially within Eddisbury. The corresponding number for those entirely within Eddisbury is 52.
These figures are subject to change.
Secondary information
- Type
- Written question
- Reference
- 10295
- Session
- 2017-19
- Subjects
- Access Land Surveys Eddisbury High Speed 2 line
- Contains statistics
- Yes
- Link
- View this Written question on www.parliament.uk
Librarians' tools
- Timestamp
- 2021-12-31 22:17:44 +0000
- URI
- http://data.parliament.uk/writtenparliamentaryquestion/commons/2017-19/10295
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/writtenparliamentaryquestion/commons/2017-19/10295
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/writtenparliamentaryquestion/commons/2017-19/10295